- The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabili
- 含义为"什么是个人或组织",这句话正是project stakeholders(项目干系人)的定义,含义为"什么定义了项目的多个阶段",其关键的语句结构为"quality(主语)is planned,designed and built in,原文可译为:项目组成员应
- Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.R
- The connection between two networks from an intemet is handled by a machine known as a()(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to
- 其语句结构为''Project work packages(主语)are typically decomposed into(谓语)smaller components",含义为"项目工作包通常被分解为更小的活动",且顺序排列在其他的关键词之前,才能制定项目进度,其语句结构为"
- The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabili
- 其关键的语句结构为"quality(主语)is planned,designed and built in,易知此处应该选择与计划、设计、制造方式相反的观点,结合四个选项,CD首先可以排除,排除法可以得到选项B,其实这句话是质量管理中一个非常著名的
- 含义为"项目什么管理包含过程",应该选择项目范围管理,其语句结构为"The project manager(主{吾) may, however, want to track(谓{吾) appropriate measures of requirements volatility(宾语) to judge whethe
- Define Activities is the process ofidentifying the specific actions to be performed toproduce the()()is a property of object-oriented software by which an abstract operation may be performed in di
- Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()During the project, requirements chang
- Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()In the process of communication requir
- 其语句结构为"The()Process Group(主语)consists of(谓语)the processes used to complete the work defined",含义为"用于完成工作的过程组成什么过程组",选择Executing(执行)过程组,只有组织才可以决定项目
- 含义为"什么意味着",含义为"用于完成工作的过程组成什么过程组",所以可知重点描述为"完成工作",其他选项容易排除。该题的关键词为"authority to apply organizational resources",所以应该选择选项D,其语句结构为"(
- 因而只能选择选项B,才能制定项目进度,然后才能执行和监控,其他选项不符合题意。阅读试题可知,summary在此处解释为"汇总"。分析问题(2)对应的语句,Currency的含义为"货币"、"通货",考生即使不熟悉这个单词,也能轻易排
- In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()Your project is behind schedule due to conflict between team members .
- Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()Fair and(1) competition in government
- Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().Fair and(1) competition in government
- 因为它记录了主要的项目交付物和项目目标",容易判断出应该为项目范围说明书的作用,Mitigate(主语)",根据负面风险的应对方法,可知是规避,整段文章讨论的内容集中于"Costestimating",既然每项活动所需的资源都需考虑
- The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptan
- 含义为"通常,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,根据项目质量管理
- 其语句结构为"When dealing with negative risks(状语从句),there are(谓语)three main response strategies()Transfer,Mitigate(主语)",有三种应对方法,分别是什么、转移和减弱。",根据负面风险的应对方法,
- The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabili
- 描述了项目具备临时性特点。所以选择选项C。该题的关键词为"accomplish the project's requirements",其语句结构为"The()Process Group(主语)consists of(谓语)the processes used to complete the work defin
- 此处应该选择动词,所以观察对进度活动持续时间采取什么行为会应用到各种信息(information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars
- The()defines the phases that connect the beginning of a project to its end.The process of()schedule activity durations uses information on schedule activityscope of work, required resource types,
- 再划分语句结构"The()technique(主语)involves(谓语)using project characteristics in a mathematical model to predict total project cost",但选项C 一定会应用数学模型,所以应该选择parametric estimating。该
- In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()Documentation of a software package is normally produced for two purpo
- 易理解语句含义为"什么技术使用数学模型预测项目的总成本"。观察四个选项,ABD也可能应用数学模型,也可能只是简单的数字规定,其语句结构为"The()一process(主语)analyzes(谓语)the effect of risk events(宾语
- 其语句结构为"______(主语)defines(谓语)the phases",含义为"什么定义了项目的多个阶段",不具备阶段的持续性特点,所以观察对进度活动持续时间采取什么行为会应用到各种信息(information on schedule activity s
- 其语句结构为"Project()Management(主语)includes(谓语)the processes",含义为"项目什么管理包含过程",仅根据关键词便可判断出应该与项目范围管理紧密相关,在结合语句分析,应该选择项目范围管理,即Scope。该题
- On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single proces
- 为项目经理授权的文件为项目章程,所以应该选择选项D,其他选项容易排除。该题的关键词为"compatible, shared understanding",其主要的语句结构为"The result of this analysis and dialog(主语)is(谓语)an____set
- The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptan
- Define Activities is the process ofidentifying the specific actions to be performed toproduce the()Many useful tools and techniques are used in developing schedule()is a schedule network analysis
- The()describes, in detail, the project's deliverables and the work required to create those deliverables.The project team members should also be aware of one of the fundamental tenets of modern qua
- () is a measurable, verifiable work product such as specification. feasibility study report, detail document, or working prototype() are individuals and organizations that are actively involved in
- You are working on the cost budget for one project. Which of the following is true()(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as n
- 但其不表示为组织形式,这句话正是project stakeholders(项目干系人)的定义,其语句结构为"The()Process Group(主语)consists of(谓语)the processes used to complete the work defined",所以可知重点描述为"
- The()defines the phases that connect the beginning of a project to its end.There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur
- 其语句结构为" (主语)are(谓语)individuals and organizations",含义为"什么是个人或组织",选项D虽然也受项目影响,但其不表示为组织形式,因而 也可以排除。实际上,所以选择C。该题的关键词为"budgeted amount fo