[单选题]() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
正确答案 :C
projectstakeholders
解析:该题的关键词为"individuals and organizations、 be affected、 exertinfluence",其语句结构为" (主语)are(谓语)individuals and organizations",含义为"什么是个人或组织",选项A和B容易排除,选项D虽然也受项目影响,也可以施加影响,但其不表示为组织形式,因而 也可以排除。实际上,这句话正是project stakeholders(项目干系人)的定义,所以选择C。
[单选题]() from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
正确答案 :D
Deliverables
解析:该题的关键词为"from one phase. reviewed. the next phase",其语句结构为" ()fromone phase(主语)are usually reviewed(谓语)for completeness and accuracy and approved before work starts on the next phase",含义为"在开始下阶段之前,需要评审前阶段什么的完整性和准确性",结合选项分析,容易排除A和B,选项C过于笼统,因而选择选项D。
[单选题]Contract closeout is a process that involves()
正确答案 :D
Product verification and administrative closeout
[单选题]There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.
正确答案 :D
Acceptance
[单选题]Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.
正确答案 :