• [单选题]The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
  • 正确答案 :A
  • estimating

  • 解析:该题的关键词为"schedule activity durations",其语句结构为"The process(主语)of()schedule activity durations uses(谓语)information",语句的含义为"(?)进度活动持续时间的过程使用信息",结合选项,此处应该选择动词,所以观察对进度活动持续时间采取什么行为会应用到各种信息(information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities),只有在估算进度活动持续时间时才会使用这些信息得到活动的工期,其他选项容易排除,因而选项A符合题意要求。

  • [单选题]On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.
  • 正确答案 :D
  • schedule development

  • 解析:该题的关键词为"activitysequencing. activity resourceestimating. Activityduration estimating",其语句结构为"activity sequencing, activity resource estimating, activity duration estimating, and (主语)are so tightly linked(谓语)",含义为"活动排序、活动资源估算、活动工期估算以及什么紧密相关",该题考察的知识点在于项目进度管理包含的各个子过程,依次为活动定义、活动排序、活动资源估算、活动工期估算、制定进度计划以及进度监控。考生在了解知识点的前提下能够轻松选出选项D,考生如果缺乏相应的知识,则只能碰运气了。

  • [单选题]In approximating costs, the estimator considers the possible causes ofvariation of the cost estimates, including()
  • 正确答案 :C
  • risk

  • 解析:该题的关键词为"approximating costs、 causes ofvariation",其语句结构为"the estimator (主语)considers(谓语)the possible causes ofvariation of the cost estimates, including()",含义为"估算人员考虑对成本估算可能造成影响的原因,包括什么"。估算成本考虑不确定性,而不确定性正是风险的一个基本特征,所以选择选项C。

  • [单选题]An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
  • 正确答案 :

  • [单选题]You are working on the cost budget for one project. Which of the following is true()
  • 正确答案 :B
  • The cost baseline will be used to measure variances and future project performance.


  • 查看原题 查看所有试题