正确答案: D
Product verification and administrative closeout
题目:Contract closeout is a process that involves()
查看原题 查看所有试题
学习资料的答案和解析:
[单选题]() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
scopeverification
解析:该题的关键词为"obtaining the stakeholders' formal acceptance、 verifying the scope",其语句结构为" (主语)1S(谓语)the process of obtaining the stakeholders' formal acceptance ofthe completed project scope",含义为"什么过程是为已完成的项目范围获取干系人的正式验收",选项B对项目的范围进行验证,其他选项容易排除。
[单选题]()involves using mathematical techniques to forecast future outcomes based onhistorical results.
Trendanalysis
解析:该题的关键词为"mathematical techniques、 forecast future outcomes",其语句结构为"____(主语)involves(谓语)using mathematical techniques to forecast future outcomes(宾语从句)",含义为"什么涉及使用数学方法预测未来结果",结合选项分析,虽然都是质量管理方法,但其中只有Trend analysis用于预测未来结果,Quality audit为质量审计,Defect repair review为缺陷补救审查,Flowcharting为流程图,均不涉及对未来结果进行预测。
[单选题]Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.