正确答案:

题目:Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.

查看原题 查看所有试题

学习资料的答案和解析:

  • [单选题]Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
  • performingorganization

  • 解析:该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

  • [单选题]The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.
  • scope statement

  • 解析:该题的关键词为"major project deliverables、the project objectives",其语句结构为"The project (主语)is(谓语)akey input to quality planning(表语)since it documentsmaj or proj ect deliverables,the project objectives(原因状语从句)",含义为"项目的什么是质量计划的一个关键输入,因为它记录了主要的项目交付物和项目目标",容易判断出应该为项目范围说明书的作用,应该选择选项B。

  • [单选题]Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.
  • Critical chain method


  • [单选题]Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()
  • change control board


  • [单选题]An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

  • [单选题]An example of scope verification is ().
  • review the performance ofan installed software module