[单选题]()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
正确答案 :B
Earned value
解析:该题的关键词为"budgeted amount for the work actually completed",其语句结构为"()(主语)is(谓语)the budgeted amount for the work actually completed",含义为"什么是实际完成工作对应的预算",容易判断该语句正是挣值( Earned value)的定义。
[单选题]The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understanding is reached on the meaning of the requirements. The result ofthis analysis and dialog is an()set of requirements.
正确答案 :A
agreed-to
解析:该题的关键词为"compatible, shared understanding",其主要的语句结构为"The result of this analysis and dialog(主语)is(谓语)an____set of requirements(表语)",含义为"分析和讨论对应的结果为一组什么的需求",根据题意,应该是达成一致的需求集,所以从选项中识别短语,判断短语的正确形式,此处应该选择agreed-t0。agree with表示同意某人,agree to表示同意某事,此处的"同意"作为形容词性质出现,所以应该使用agreed to形式,其他都不对。
[单选题]Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.
正确答案 :D
Critical chain method
[单选题]Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
正确答案 :D
workpackage
[单选题]An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
正确答案 :
查看原题 查看所有试题