题目:In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.
解析:翻译如下:
查看原题 查看所有试题
学习资料的答案和解析:
[单选题]在进行项目活动历时估算时,()属于参数估算
B、用需要完成工作的数量乘以完成单位工作所需时间作为估算活动时间的依据
解析:参数估算是利用历史数据和一些变量之间的统计关系,计算活动资源成本或历时。
[单选题]In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.
schedule
[单选题]选择推荐中,不应当在对比方案中体现的是()
将乙方获利最丰的因素放在显著的位置
[单选题]在建立项目变更控制之前必须先完成:()
基线(BaselinE.