• [单选题]In the project management context()includes characteristics of unification,consolidation, articulation, and integrative actions that are crucial to project completion,successfully meeting customer and other stakeholder requirements, and managing expectations.
  • 正确答案 :A
  • integration

  • 解析:该题的关键词为"unification、consolidation、articulation、integrativeactions",其语句结构为"(主语)includes(谓语)characteristics of unification,consolidation,articulation,andintegrativeactions",含义为"什么包括了统一、合并、沟通的特征以及集成活动",根据语句的含义容易识别为集成(或整体),对应的英文为Integration。

  • [单选题]On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.
  • 正确答案 :D
  • schedule development

  • 解析:该题的关键词为"activitysequencing. activity resourceestimating. Activityduration estimating",其语句结构为"activity sequencing, activity resource estimating, activity duration estimating, and (主语)are so tightly linked(谓语)",含义为"活动排序、活动资源估算、活动工期估算以及什么紧密相关",该题考察的知识点在于项目进度管理包含的各个子过程,依次为活动定义、活动排序、活动资源估算、活动工期估算、制定进度计划以及进度监控。考生在了解知识点的前提下能够轻松选出选项D,考生如果缺乏相应的知识,则只能碰运气了。

  • [单选题]Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.
  • 正确答案 :B
  • QualityFunctionDeployment


  • 查看原题 查看所有试题