正确答案: B
Projectized
题目:In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
查看原题 查看所有试题
学习资料的答案和解析:
[单选题]()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.These other projects can be within the performing organization or outside of it,and can be within the same or in another application area.
Benchmarking
解析:该题的关键词为"comparing actual or planned project practices to those of other proj ects",其语句结构为"()(主语)involves(谓语)comparing actual or planned project practices to those of other projects",含义为"什么涉及到将实际或计划的项目实践同其他项目实践比较",比较项目实践是质量管理方法比较基准(Benchmarking)的主要特征。因而选择选项C。
[单选题]()involves using mathematical techniques to forecast future outcomes based onhistorical results.
Trendanalysis
解析:该题的关键词为"mathematical techniques、 forecast future outcomes",其语句结构为"____(主语)involves(谓语)using mathematical techniques to forecast future outcomes(宾语从句)",含义为"什么涉及使用数学方法预测未来结果",结合选项分析,虽然都是质量管理方法,但其中只有Trend analysis用于预测未来结果,Quality audit为质量审计,Defect repair review为缺陷补救审查,Flowcharting为流程图,均不涉及对未来结果进行预测。
[单选题]Define Activities is the process ofidentifying the specific actions to be performed toproduce the()
projectdeliverables
解析:该题的关键词为"Define Activities、identifying the specific actions",其语句结构为"Define Activities(主语)is(谓语)the process ofidentifying the specific actions to beperformed to produce the_ ",含义为"活动定义是为了生成什么而执行所识别出的特定活动",这是考察进度管理知识领域中的活动定义的概念,活动定义是为了生成交付物或子交付物而执行的活动,因此选择选项D。
[单选题]Contract closeout is a process that involves()
Product verification and administrative closeout