[单选题]Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work.
正确答案 :B
estimating
解析:该题的关键词为"scheduling、executing、monitoring、controlling",其语句结构为''Project work packages(主语)are typically decomposed into(谓语)smaller components",含义为"项目工作包通常被分解为更小的活动",分析后得知空白处的选项应该和上述的关键词为并列的词语,且顺序排列在其他的关键词之前,因而只能选择选项B,因为只有首先进行项目估算,才能制定项目进度,然后才能执行和监控,其他选项不符合题意。
[单选题]The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.
正确答案 :A
subdividing
解析:该题的关键词为"work breakdown structure、 major project deliverables",其语句结构为"The creation ofa work breakdown structure (WBS)(主语)is(谓语)the processof()the major project deliverables",含义为"创建WBS是怎样主要的项目交付物的过程"。根据WBS定义以及选项,容易识别出应选择分解(subdividing)