[单选题]On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.
正确答案 :D
schedule development
解析:该题的关键词为"activitysequencing. activity resourceestimating. Activityduration estimating",其语句结构为"activity sequencing, activity resource estimating, activity duration estimating, and (主语)are so tightly linked(谓语)",含义为"活动排序、活动资源估算、活动工期估算以及什么紧密相关",该题考察的知识点在于项目进度管理包含的各个子过程,依次为活动定义、活动排序、活动资源估算、活动工期估算、制定进度计划以及进度监控。考生在了解知识点的前提下能够轻松选出选项D,考生如果缺乏相应的知识,则只能碰运气了。
[单选题]The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.
正确答案 :B
scope statement
解析:该题的关键词为"major project deliverables、the project objectives",其语句结构为"The project (主语)is(谓语)akey input to quality planning(表语)since it documentsmaj or proj ect deliverables,the project objectives(原因状语从句)",含义为"项目的什么是质量计划的一个关键输入,因为它记录了主要的项目交付物和项目目标",容易判断出应该为项目范围说明书的作用,应该选择选项B。
[单选题]Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.
正确答案 :B
QualityFunctionDeployment