正确答案: B

QualityFunctionDeployment

题目:Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.

查看原题 查看所有试题

学习资料的答案和解析:

  • [单选题]PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
  • Start-to-Finish

  • 解析:该题的关键词为"PDM includes four types",其语句结构为"The completion of the successor activity(主语)depends upon(谓语)the initiation of the predecessor activity",含义为"后续活动的完成依赖于前置活动的开始",根据选项容易识别为SF活动依赖类型。

  • [单选题]()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
  • Earned value

  • 解析:该题的关键词为"budgeted amount for the work actually completed",其语句结构为"()(主语)is(谓语)the budgeted amount for the work actually completed",含义为"什么是实际完成工作对应的预算",容易判断该语句正是挣值( Earned value)的定义。

  • [单选题]In approximating costs, the estimator considers the possible causes ofvariation of the cost estimates, including()
  • risk

  • 解析:该题的关键词为"approximating costs、 causes ofvariation",其语句结构为"the estimator (主语)considers(谓语)the possible causes ofvariation of the cost estimates, including()",含义为"估算人员考虑对成本估算可能造成影响的原因,包括什么"。估算成本考虑不确定性,而不确定性正是风险的一个基本特征,所以选择选项C。

  • [单选题]Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
  • activity resource estimating, activity duration estimating, schedule development


  • [单选题]Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.

  • [单选题]Fair and(1) competition in government procurement around the world is good business and good public policy. Competitive pricing, product(2)and performanceimprovements result from competitive practices and help ensure that government authoritiesget the best (3)for the public they serve.

  • [单选题]Documentation of a software package is normally produced for two purposes. One is to explain the (1) ofthe software and describe how to use them. This is known as (2) because it is designed to be read by the user of the software. The other purpose of documentation is to describe the software's internal composition so that the system can be maintained later in its life cycle. Documentation ofthis type is known as ( 3 )