正确答案: B

Earned value

题目:()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.

解析:该题的关键词为"budgeted amount for the work actually completed",其语句结构为"()(主语)is(谓语)the budgeted amount for the work actually completed",含义为"什么是实际完成工作对应的预算",容易判断该语句正是挣值( Earned value)的定义。

查看原题 查看所有试题

学习资料的答案和解析:

  • [单选题]Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage,retrieval, and ultimate disposition ofproject information.
  • Communication

  • 解析:该题的关键词较多,不过都是并列的关系,包括"ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition、 projectinformation"。其主要语句结构为"Project()Management(主语)is(谓语)the Knowledge Area",含义为"项目什么管理是知识领域",后续的定语从句说明该知识领域的特点。其实根据关键词"Proj ect information"考生可以很容易识别出来应该是项目沟通管理。

  • [单选题]Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.
  • work

  • 解析:该题的关键词为"required resource types、estimated resource quantities、 resource calendars",其语句结构为"Estimating activity durations(主语)uses(谓语)information on activity scope of_____(宾语)",含义为"估算活动工期应用什么活动范围的信息",结合前面的关键词,此处应该识别出估算活动工期对应的输入项,因而选择工作范围,选择选项D。

  • 推荐下载科目: 计算机网络知识题库 法律法规和标准规范题库 信息安全知识题库 初级信息处理技术员题库 项目风险管理题库 项目沟通管理题库 项目质量管理题库 项目采购管理题库 战略管理概述题库 业务流程管理和重组题库
    @2019-2025 必典考网 www.51bdks.net 蜀ICP备2021000628号 川公网安备 51012202001360号