• [单选题]The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
  • 正确答案 :A
  • estimating

  • 解析:该题的关键词为"schedule activity durations",其语句结构为"The process(主语)of()schedule activity durations uses(谓语)information",语句的含义为"(?)进度活动持续时间的过程使用信息",结合选项,此处应该选择动词,所以观察对进度活动持续时间采取什么行为会应用到各种信息(information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities),只有在估算进度活动持续时间时才会使用这些信息得到活动的工期,其他选项容易排除,因而选项A符合题意要求。

  • [单选题]()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
  • 正确答案 :B
  • Earned value

  • 解析:该题的关键词为"budgeted amount for the work actually completed",其语句结构为"()(主语)is(谓语)the budgeted amount for the work actually completed",含义为"什么是实际完成工作对应的预算",容易判断该语句正是挣值( Earned value)的定义。

  • [单选题]() from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
  • 正确答案 :D
  • Deliverables

  • 解析:该题的关键词为"from one phase. reviewed. the next phase",其语句结构为" ()fromone phase(主语)are usually reviewed(谓语)for completeness and accuracy and approved before work starts on the next phase",含义为"在开始下阶段之前,需要评审前阶段什么的完整性和准确性",结合选项分析,容易排除A和B,选项C过于笼统,因而选择选项D。

  • [单选题]Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.
  • 正确答案 :B
  • QualityFunctionDeployment


  • 查看原题 查看所有试题