必典考网

高级信息系统项目管理师题库2022专业英语题库相关专业每日一练(09月08日)

来源: 必典考网    发布:2022-09-08     [手机版]    
  • 下载次数:
  • 支持语言:
  • 1692次
  • 中文简体
  • 文件类型:
  • 支持平台:
  • pdf文档
  • PC/手机

导读

必典考网发布高级信息系统项目管理师题库2022专业英语题库相关专业每日一练(09月08日),更多专业英语题库的每日一练请访问必典考网高级信息系统项目管理师题库频道。

1. [单选题]The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.

A. estimating
B. defining
C. planning
D. sequencing


2. [单选题]On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.

A. time estimating
B. cost estimating
C. project planning
D. schedule development


3. [单选题]In approximating costs, the estimator considers the possible causes ofvariation of the cost estimates, including()

A. budget
B. plan
C. risk
D. contract


4. [单选题]An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

A. A


5. [单选题]You are working on the cost budget for one project. Which of the following is true()

A. This process assigns cost estimates to project activities including risks and contingency plans.
B. The cost baseline will be used to measure variances and future project performance.
C. This process assigns cost estimates for expected future period operating costs.
D. The cost baseline is the expected cost for the project.


  • 查看答案&解析 查看所有试题

  • 本文链接:https://www.51bdks.net/show/yp33e6.html

    @2019-2025 必典考网 www.51bdks.net 蜀ICP备2021000628号 川公网安备 51012202001360号