1. [单选题]The()defines the phases that connect the beginning of a project to its end.

A. schedule
B. project life cycle
C. temporary
D. milestone


2. [单选题]The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.

A. estimating
B. defining
C. planning
D. sequencing


3. [单选题]Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

A. performance
B. process
C. product
D. object


4. [单选题]()involves using mathematical techniques to forecast future outcomes based onhistorical results.

A. Trendanalysis
B. Qualityaudit
C. Defect repair review
D. Flowcharting


5. [单选题]The (1) is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several (2).