1. [单选题]The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

A. costaggregation
B. reserve analysis
C. parametricestimating
D. funding limit reconciliation


2. [单选题]PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.

A. Finish-to-Start
B. Finish-to-Finish
C. Start-to-Start
D. Start-to-Finish


3. [单选题]On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.

A. time estimating
B. cost estimating
C. project planning
D. schedule development


4. [单选题]Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

A. activity duration estimating, schedule developing, activity resource estimating
B. activity resource estimating, activity duration estimating, schedule development
C. schedule developing, activity resource estimating, activity duration estimating
D. activity resource estimating, schedule developing, activity duration estimating


5. [单选题]Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

A. executive IT manager
B. projectmanger
C. change control board
D. projectsponsor


6. [单选题]The connection between two networks from an intemet is handled by a machine known as a()

A. bridge
B. server
C. router
D. switch


7. [单选题]The (1) is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several (2).

A. A


8. [单选题]Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.

A. D


9. [单选题]Documentation of a software package is normally produced for two purposes. One is to explain the (1) ofthe software and describe how to use them. This is known as (2) because it is designed to be read by the user of the software. The other purpose of documentation is to describe the software's internal composition so that the system can be maintained later in its life cycle. Documentation ofthis type is known as ( 3 )

A. C


  • 查看答案&解析 查看所有试题