【名词&注释】
质量管理、基本原则(basic principle)、关键词、排除法(exclusive method)、过去分词(past participle)、项目组成员
[单选题]The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()
A. executedin
B. inspectedin
C. check-in
D. look-in
查看答案&解析
查看所有试题
学习资料:
[单选题]()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A. Plannedvalue
B. Earned value
C. Actualcost
D. Costvariance
[单选题]Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.
A. Integration
B. Scope
C. Configuration
D. Requirement
[单选题]()is a category assigned to products or services having the samefunctional use but different technical characteristics. Itisnotsameasquality.
A. Problem
B. Grade
C. Risk
D. Defect
[单选题]Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().
A. crashing the schedule
B. performing resource leveling
C. conducting reverse resource allocation scheduling
D. utilizing the critical chain resources