1. [单选题]The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.

A. estimating
B. defining
C. planning
D. sequencing


2. [单选题]The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.

A. work performance information
B. scope statement
C. changerequests
D. process analysis


3. [单选题]Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.

A. analyze
B. track
C. level
D. extend


4. [单选题]In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

A. Strongmatrix
B. Projectized
C. Projectcoordinator
D. Weakmatrix


5. [单选题]In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.

A. 10
B. 45
C. 50
D. 100