1. [单选题]The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

A. costaggregation
B. reserve analysis
C. parametricestimating
D. funding limit reconciliation


2. [单选题]The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

A. Riskldentification
B. Quantitative RiskAnalysis
C. Qualitative RiskAnalysis
D. Risk Monitoring and Control


3. [单选题]During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.

A. proceedings
B. controls
C. forecastings
D. Prelibations


4. [单选题]Define Activities is the process ofidentifying the specific actions to be performed toproduce the()

A. projectelements
B. work drafts
C. workpackage
D. projectdeliverables


5. [单选题]Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work.

A. reviewing
B. estimating
C. auditing
D. expecting


6. [单选题]Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.

A. PERT
B. Resourceleveling
C. Schedulecompression
D. Critical chain method


7. [单选题](1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.

A. D


8. [单选题]Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.

A. A


9. [单选题]Fair and(1) competition in government procurement around the world is good business and good public policy. Competitive pricing, product(2)and performanceimprovements result from competitive practices and help ensure that government authoritiesget the best (3)for the public they serve.

A. B


10. [单选题]Fair and(1) competition in government procurement around the world is good business and good public policy. Competitive pricing, product(2)and performanceimprovements result from competitive practices and help ensure that government authoritiesget the best (3)for the public they serve.

A. C