1. [单选题]The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A. estimating
B. defining
C. planning
D. sequencing
2. [单选题]The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()
A. executedin
B. inspectedin
C. check-in
D. look-in