[单选题]Fair and(1) competition in government procurement around the world is good business and good public policy. Competitive pricing, product(2)and performanceimprovements result from competitive practices and help ensure that government authoritiesget the best (3)for the public they serve.
A. C
查看答案&解析
查看所有试题
学习资料:
[单选题]The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A. estimating
B. defining
C. planning
D. sequencing
[单选题]Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()
A. confused
B. same
C. overlap
D. dissever
[单选题]The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
A. Riskldentification
B. Quantitative RiskAnalysis
C. Qualitative RiskAnalysis
D. Risk Monitoring and Control
[单选题]During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.
A. proceedings
B. controls
C. forecastings
D. Prelibations
[单选题]Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
A. independentresource
B. individualworkload
C. workmilestone
D. workpackage
[单选题]An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
A. A
[单选题](1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.
A. D