[单选题]Contract closeout is a process that involves()
A. Customer satisfaction analysis and final payment
B. Administrative closeout and archiving records
C. Finial contractor payment and Lessons learned
D. Product verification and administrative closeout
查看答案&解析
查看所有试题
学习资料:
[单选题]() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
A. projectacceptance
B. scopeverification
C. scopedefinition
D. WBS Creation
[单选题]()involves using mathematical techniques to forecast future outcomes based onhistorical results.
A. Trendanalysis
B. Qualityaudit
C. Defect repair review
D. Flowcharting
[单选题]Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.
A. D