1. [单选题]The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.
A. costaggregation
B. reserve analysis
C. parametricestimating
D. funding limit reconciliation
2. [单选题]The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
A. Riskldentification
B. Quantitative RiskAnalysis
C. Qualitative RiskAnalysis
D. Risk Monitoring and Control
3. [单选题]During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.
A. proceedings
B. controls
C. forecastings
D. Prelibations