1. [单选题]() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.

A. controls
B. baselines
C. projectstakeholders
D. projectmanagers


2. [单选题]()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.

A. Plannedvalue
B. Earned value
C. Actualcost
D. Costvariance


3. [单选题]()involves using mathematical techniques to forecast future outcomes based onhistorical results.

A. Trendanalysis
B. Qualityaudit
C. Defect repair review
D. Flowcharting


4. [单选题]Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

A. Benefitcontribution
B. Expertjudgment
C. Scoringmodels
D. Flowcharting


5. [单选题](1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.

A. A