【导读】
必典考网发布专业英语题库2022易混易错每日一练(06月05日),更多专业英语题库的每日一练请访问必典考网高级信息系统项目管理师题库频道。
1. [单选题]()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.These other projects can be within the performing organization or outside of it,and can be within the same or in another application area.
A. Metrics
B. Measurement
C. Benchmarking
D. Baseline
2. [单选题]The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal ofthe plan is to minimize threats and maximize opportunities. When dealing with negative risks, there are three main response strategies(),rransfer ,Mitigate.
A. Challenge
B. Exploit
C. Avoid
D. Enhance
3. [单选题]Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.
A. RationalClearcase
B. QualityFunctionDeployment
C. VisualSourceSafe
D. ConcurrentVersions System
4. [单选题]In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
A. Strongmatrix
B. Projectized
C. Projectcoordinator
D. Weakmatrix
5. [单选题]Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the (2) and must develop enough knowledge about the (3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.
A. C