必典考网

专业英语题库2022考前模拟考试140

来源: 必典考网    发布:2022-05-21     [手机版]    
  • 下载次数:
  • 支持语言:
  • 1960次
  • 中文简体
  • 文件类型:
  • 支持平台:
  • pdf文档
  • PC/手机

导读

必典考网发布专业英语题库2022考前模拟考试140,更多专业英语题库的模拟考试请访问必典考网高级信息系统项目管理师题库频道。

1. [单选题]()means that every project has a definite beginning and a definite end.

A. Projectphase
B. Unique
C. Temporary
D. Closure


2. [单选题]On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.

A. time estimating
B. cost estimating
C. project planning
D. schedule development


3. [单选题]Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage,retrieval, and ultimate disposition ofproject information.

A. Integration
B. Time
C. Planning
D. Communication


4. [单选题]Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

A. Project
B. project management team
C. performingorganization
D. customer


5. [单选题]Performing()involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.

A. qualityplanning
B. qualityassurance
C. qualityperformance
D. quality control


6. [单选题]Define Activities is the process ofidentifying the specific actions to be performed toproduce the()

A. projectelements
B. work drafts
C. workpackage
D. projectdeliverables


7. [单选题]Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

A. independentresource
B. individualworkload
C. workmilestone
D. workpackage


8. [单选题]Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

A. Benchmarking
B. Quality metric
C. Quality checklist
D. Brainstornung


9. [单选题]There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.

A. share
B. Mitigate
C. Transfer
D. Acceptance


10. [单选题]The (1) is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several (2).

A. B


  • 查看答案&解析 查看所有试题

  • 本文链接:https://www.51bdks.net/show/l976wy.html

    @2019-2025 必典考网 www.51bdks.net 蜀ICP备2021000628号 川公网安备 51012202001360号