  • [单选题]The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.

  • A. The communication management plan is contained in or is a subsidiary plan of, the project management plan.
    B. The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.
    C. The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
    D. The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail

  • 查看答案&解析 查看所有试题
  • 学习资料:
  • [单选题]在需求开发中,完成()过程后将确定需求基线
  • A. 需求获取
    B. 需求分析
    C. 需求定义
    D. 需求验证

  • [单选题]The most crucial time for project risk assessment is ().
  • A. when a problem surfaces
    B. during the planning phase
    C. during the close-out phase
    D. after the project schedule has been published

  • [单选题]针对大型IT项目,下列选项中()是不正确的。
  • A. 大型IT项目一般是在需求不十分清晰的情况下开始的,所以需要对项目进行阶段性分解
    B. 通常由专业的咨询公司对需求进行详细的定义
    C. 使用甘特图制定项目的进度计划
    D. 项目需求定义和需求实现通常都是一方完成的

  • [单选题]T和H分别作为系统需求分析师和软件设计工程师,参与①、②、③、④四个软件的开发工作。T的工作必须发生在H开始工作之前。每个软件开发工作需要的工时如下表所示。在最短的软件开发工序中,单独压缩()对进一步加快进度(speeding up construction progress)没有帮助。
  • A. ①的需求分析时间
    B. ①的软件设计时间
    C. ③的需求分析时间
    D. ③的软件设计时间