1. [单选题]() is a measurable, verifiable work product such as specification. feasibility study report, detail document, or working prototype
A. milestone
B. deliverable
C. etc
D. BAC
2. [单选题]()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A. Plannedvalue
B. Earned value
C. Actualcost
D. Costvariance
3. [单选题]Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are()
A. confused
B. same
C. overlap
D. dissever
4. [单选题]Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.
A. Integration
B. Scope
C. Configuration
D. Requirement
5. [单选题]On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.
A. time estimating
B. cost estimating
C. project planning
D. schedule development
6. [单选题]The receiving activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understanding is reached on the meaning of the requirements. The result ofthis analysis and dialog is an()set of requirements.
A. agreed-to
B. agree-to
C. agree-to-do
D. agree-with
7. [单选题]Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.
A. analyze
B. track
C. level
D. extend
8. [单选题]The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal ofthe plan is to minimize threats and maximize opportunities. When dealing with negative risks, there are three main response strategies(),rransfer ,Mitigate.
A. Challenge
B. Exploit
C. Avoid
D. Enhance
9. [单选题]The Unified Modeling Language is a standard graphical language for modeling object-oriented software()can show the behavior of systems in terms of how objects interact with each other.
A. Classdiagram
B. Componentdiagram
C. Sequencediagram
D. Use case diagram