1. [单选题]On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.

A. time estimating
B. cost estimating
C. project planning
D. schedule development


2. [单选题]The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.

A. work performance information
B. scope statement
C. changerequests
D. process analysis


3. [单选题]Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.

A. RationalClearcase
B. QualityFunctionDeployment
C. VisualSourceSafe
D. ConcurrentVersions System