Project schedule management is made up of six management pro

  • 下载次数:
  • 支持语言:
  • 441
  • 中文简体
  • 文件类型:
  • 支持平台:
  • pdf文档
  • PC/手机
  • 【名词&注释】

    持续性(persistence)、关键词、知识点(knowledge point)、里程碑(milestone)、不具备(does not have)、可表示(can be expressed)

  • [单选题]Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.

  • A. activity duration estimating, schedule developing, activity resource estimating
    B. activity resource estimating, activity duration estimating, schedule development
    C. schedule developing, activity resource estimating, activity duration estimating
    D. activity resource estimating, schedule developing, activity duration estimating

  • 查看答案&解析 查看所有试题
  • 学习资料:
  • [单选题]The()defines the phases that connect the beginning of a project to its end.
  • A. schedule
    B. project life cycle
    C. temporary
    D. milestone

  • [单选题]The Unified Modeling Language is a standard graphical language for modeling object-oriented software()can show the behavior of systems in terms of how objects interact with each other.
  • A. Classdiagram
    B. Componentdiagram
    C. Sequencediagram
    D. Use case diagram