【名词&注释】
关键词、可验证的
[单选题]Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()
A. executive IT manager
B. projectmanger
C. change control board
D. projectsponsor
查看答案&解析
查看所有试题
学习资料:
[单选题]() is a measurable, verifiable work product such as specification. feasibility study report, detail document, or working prototype
A. milestone
B. deliverable
C. etc
D. BAC
[单选题]You are working on the cost budget for one project. Which of the following is true()
A. This process assigns cost estimates to project activities including risks and contingency plans.
B. The cost baseline will be used to measure variances and future project performance.
C. This process assigns cost estimates for expected future period operating costs.
D. The cost baseline is the expected cost for the project.
[单选题]In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
A. Strongmatrix
B. Projectized
C. Projectcoordinator
D. Weakmatrix
[单选题]Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
A. Benchmarking
B. Quality metric
C. Quality checklist
D. Brainstornung