[单选题]An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
A. A
查看答案&解析
查看所有试题
学习资料:
[单选题]() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
A. projectacceptance
B. scopeverification
C. scopedefinition
D. WBS Creation
[单选题]The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()
A. executedin
B. inspectedin
C. check-in
D. look-in
[单选题]Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().
A. crashing the schedule
B. performing resource leveling
C. conducting reverse resource allocation scheduling
D. utilizing the critical chain resources
[单选题]The (1) is a general description of the architecture of a workflow management system used by the WFMC, in which the main components and the associated interfaces are summarized. The workflow enactment service is the heart of a workflow system which consists of several (2).
A. B